Bluebonnet Elementary School is the newest campus in Lockhart ISD. It was constructed in 2005 and serves PK-5th grade. With almost 69,000sf, the campus has a functional capacity of just over 600 students.
Bond program improvements for BES include:
- Interior remodel to provide for a controlled secure entry
- Installation of A/C in the gym
| Budget: | $155,683 | |
|---|---|---|
| Architect: | Huckabee, Inc. | |
| Contractor: | Wattinger | |
| Projected Completion: | Summer 2017 | |
| Update: | At their May 18, 2015, regular meeting the Board of Trustees approved the construction contract for District wide HVAC improvements. Work was initiated upon the end of the semester. The HVAC work for the gym is now generally complete and final approval by the City was granted on August 18. Final completion of remaining improvements will be the summer of 2017. Design for the remaining improvements will begin soon. | |
Interior Duct Work![]() |
Exterior Unit and Duct Work![]() | |
| Looking ahead: |
| |